• All eight pump station roof replacements completed
• City continues electrical improvements
• Advances relief well engineering under $10.7 million federal project
Williamsport, PA – The City of Williamsport and SEDA-Council of Governments (SEDA-COG) are pleased to announce significant progress on the approximately $10.7 million FY2023 Legislative Pre-Disaster Mitigation (LPDM) Levee Improvement Project, including the successful completion of all eight pump station roof replacements, continued advancement of electrical infrastructure improvements, and progress toward the next phase of relief well engineering.

Betsy Kramer, director of Community Revitalization & Flood Resiliency at SEDA-COG, provided an update on the project during the Williamsport City Council meeting on Thursday, November 5, highlighting recent construction milestones, ongoing engineering efforts, and continued coordination with state and federal partners.
All Eight Pump Station Roof Replacements Completed
One of the project’s most significant accomplishments is the completion of roof replacements at all eight pump stations included in the project scope.
Weatherproofing Technologies, Inc. (WTI), working through the Keystone Purchasing Network (KPN), successfully completed the roof replacements, representing a major construction milestone in the City’s ongoing efforts to maintain and improve critical flood protection infrastructure.
Additional stabilization activities are underway as the project team continues coordinating remaining work.
The improvements are part of a broader effort to strengthen the reliability and long-term performance of infrastructure supporting the Greater Williamsport Area levee system.
Electrical Infrastructure Improvements Moving Forward
The project is also advancing improvements to electrical infrastructure at the City’s levee pump stations.
Following Williamsport City Council’s approval of the electrical construction contract in August 2026, Lecce Electric began coordinating project implementation with Greenman-Pedersen, Inc. (GPI), the City’s construction management and inspection consultant.
The improvements are intended to address critical electrical infrastructure needs at the pump stations and support the continued operation and reliability of the levee system.
GPI, Lecce Electric, the City, and SEDA-COG continue coordinating construction scheduling, contractor requirements, federal compliance, and implementation activities.
AECOM Advances Relief Well Engineering
Another major component of the project involves engineering improvements to the levee system’s relief wells, which play an important role in managing groundwater pressure and seepage associated with high-water events.

During the November 5 City Council meeting, Kramer also discussed a proposed engineering scope submitted by AECOM for the next phase of the relief well replacement initiative.
AECOM’s proposal, dated October 13, 2026, includes approximately 25 geotechnical borings, 10 test and pumping wells, pumping tests, seepage and stability analyses, and the development of engineering plans, specifications, and construction cost estimates.
The proposed engineering approach has been submitted to the U.S. Army Corps of Engineers (USACE) for review and concurrence.
The technical investigations and engineering work will help establish the appropriate relief well replacement strategy, refine construction requirements, and develop the information necessary to advance future construction.
Approximately $1.75 million in Pennsylvania Redevelopment Assistance Capital Program (RACP) funding has been identified for relief well construction. Additional engineering and cost development will help determine the full construction funding requirements and guide the pursuit of supplemental funding opportunities.
Federal Grant Extension Provides Additional Implementation Time
The City also recently received confirmation that the FY2023 LPDM grant’s Period of Performance amendment was formally executed, extending the project through April 30, 2028. The extension provides additional time to complete the remaining construction and engineering activities while maintaining coordination with the Pennsylvania Emergency Management Agency (PEMA), the Federal Emergency Management Agency (FEMA), and USACE.
SEDA-COG continues serving as the City’s grant administrator, supporting project coordination, federal compliance, financial documentation, reporting, and stakeholder engagement.
Regional Flood Protection and Economic Resiliency
The Greater Williamsport Area levee system is a critical component of the region’s flood protection infrastructure, supporting the safety and resiliency of residential neighborhoods, commercial districts, businesses, and essential community assets.
The ongoing improvements are part of a broader regional effort to rehabilitate and strengthen the levee system and support its long-term certification.

In September, representatives from the City of Williamsport and SEDA-COG showcased the project during the Pennsylvania Silver Jackets Flood Resiliency Projects Tour. The Northeast Williamsport Levee and Hepburn Street Pump Station served as the tour’s first stop, providing state and federal flood resiliency partners with an opportunity to observe project progress firsthand.
The initiative was also highlighted during the September Lycoming County Chamber of Commerce breakfast, emphasizing the connection between flood protection infrastructure, community resiliency, and regional economic stability.
Looking Ahead
Over the coming months, the City and its project partners will continue advancing pump station electrical improvements, completing remaining stabilization activities, coordinating AECOM’s relief well engineering approach with USACE, and managing the federal grant requirements associated with the project.
The City and SEDA-COG remain committed to working with PEMA, FEMA, USACE, engineering consultants, construction contractors, and legislative partners to advance these important infrastructure improvements.
#
SEDA-Council of Governments (SEDA-COG) is a regional public development organization serving 11 counties in central Pennsylvania. Through its Community Revitalization & Flood Resiliency program and other regional initiatives, SEDA-COG works with municipalities and community partners to advance infrastructure investment, economic development, community revitalization, and long-term resiliency.